The Construction
of a Public Toilet at Meeting hall was completed on 3rd March (as
per the Community Contract Agreement drawn between the Gewog and the Community
Group to complete it on 3rd March beginning the work from the 3rd
January) by the Neymedsa Group, a local community Group. The Gewog
Administration after being endorsed by all the GT (Gewog Tshogdu) members on 20th
December, 2014 decided to award the works in the chewogs and villages of the
Gewog for the Community having the Community’s direct Participation and also to
have a direct sense of ownership of the infrastructures and more importantly is
to have good quality of the works and the limited time period for the works to
complete it for the fiscal year 2013-2014.
It was also of
the adverse records with the Gewog Administration of
the commercial contractors for the Past Fiscal year 2012-2013 of whom some contractors
failed to complete the work on given time period despite their undertakings and
some not being able to complete its rectifications.
The Community Contractor namely Mr.Tshewang Dorji Sherpa was the Chairman of the Group with
other four members in a group. The Estimation amount/cost (engineer’s estimation)
amounted to Nu. 204000(two lakhs four Thousand) yet the approved budget was of
Nu.188000 (one lakh eighty eight thousand) only of which the Group negotiated to
work for the approved budget-one such procedure in the community Contracting Protocol-E;-Negotiation
of the Contract.
By Lobzang Choda
Rangthangling Gewog, Tsirang