The Gewog
Administration officially handed over the Maintenance of Nimazor A and B
irrigation channels today at Nimazor village to the beneficiaries of both the
schemes. There were a total of thirteen households from two schemes, six people
from Nimazor A and 7 people from Nimazor B.
The work was
executed departmentally and apart of the official handing and taking of these
two schemes today, four masons were also made a payment for the works carried
out for these schemes.
It was only
through direct participation with such handing and taking note that the
beneficiaries will feel the ownership of these infrastructures and also to
maintain the minor damages themselves and thereby ensuring the sustainability
of the schemes.
These schemes
were completed earlier in the June month and the funding were also both from
the RGOB (Royal Government of Bhutan), a planned activity and GDG (Gewog
Development Grant) for the fiscal year 2015-2016 incurring a total expenditure
of Nu. 370847.00 (Three lakhs seventy thousand eight hundred and forty seven)
only.
The Gewog
Administration is to hand over the other remaining completed schemes within
this week to the beneficiaries.