Friday, 20 March 2015

Construction of a Farm Road, Approach Road to Gewog Lhakhang.

The Construction of 0.5(half)kilometer Lhakhang Farm Road, approach Road till Gewog Lhakhang started on 17th of March by the Community contractor, Mr.Dil Bdr. Tamang as chairman of the Community Group after it was awarded to him on the basis of a lottery system of Yes and No of which he got a Yes vote amongst the three community contractors of the Gewog with the negotiation of fixed 3% from the estimated amount of Nu.11,53,463(eleven lakhs fifty three thousand and four hundred and sixty three)only and it is also one such procedure in the community Contracting Protocol-E;-Negotiation of the Contract.
And its to be completed in three months of time, i.e before June and is also one of the prioritized activity of the GDG (Gewog Development Grant) having endorsed by all the GT (Gewog Tshogdu) members for this fiscal year.

By Lobzang Choda
Rangthangling Gewog